As part of the Vision 2025 infrastructure project, three pools will be renovated over the next five months. Each renovation will take approximately 10 weeks. Work on pool 10 is underway and is expected to be completed in mid November.
Pool 5 is scheduled for mid-November (no work over the Christmas holidays) and pool 6 will start in mid to late January. More precise construction starting dates will be provided when they become available.
Residents who live close to the affected pools should be prepared for a considerable amount of construction noise and dust.
For further information contact Doug Quinn, operations project manager.